With the first glimpses of glass, this Eichler is starting to feel real… Just a few quick photos and videos this week, as things are crazy busy! Enjoy 🙂…
-
-
The bedroom and laundry room windows are installed and loads more Eichler siding is going in. We are still waiting for the All Weather windows and sliding doors, as well as the Velux skylights…
-
While we were on holiday, the SPDB team made loads of progress with the roofing subcontractors and drywall crews. The Typar waterproofing layer has been installed, and a first glimpse of the Eichler siding.…
-
Drywall folks, we have DRYWALL! As soon as we received permit sign-off the drywall went up in just 2 days time. Crazy fast! Here’s a first look at the new layout and space inside…
-
It’s starting to feel real. Electrical, plumbing and fire sprinkler permits are approved and rough-in carpentry complete. Work to close in the roof has started, which means interior insulation is a go.…
-
Wow it’s been a busy few weeks. We’ve moved in with family until the Eichler is ready, and had a whirlwind of changes around the house.…
-
We have concrete poured in the bathrooms, which means the final pieces of framing are now in place. …
-
It’s been a busy few weeks and we have a big Eichler update today. We have exterior Densglass, plumbing roughed-in, initial electrical work, and we are well into a new roof structure. Wheww!…
-
Loads of great news this week – they’ve lifted massive steel beams onto the roof and we’ve passed our first plumbing inspection. The weight has been lifted 😉…
-
No glass, no windows, no walls – no problem. Ready for inspections now that the new plumbing and drainage is prepped.…
-
Despite the rain, the SPDB team has made great progress this week, adding new sheathing to the newly framed walls. Demo continues in the bathrooms, and we start to see structural improvements and openings…
-
More progress this week as the new walls, closets and doorways have been roughly framed, and a trench dug for new electrics.…
-
Now that the asbestos is gone, the HVAC team can start planning their work. We will have to disturb some of the radiant floor heating pipes in order to upgrade the water and sewer…
-
Loads of progress this week, as we go down to the studs thanks to the asbestos abatement process.…
-
Huge step forward this week as we prep the house for the asbestos abatement company to come through and work their magic. …